SolarFuture ApS and Migra Teknik ApS
Denmark’s leading EPC contractor and PV commissioning specialist, working togetherRecord commissioning throughput: over 0.5 MW tested per hour
As solar farms continue to grow in scale, commissioning speed becomes a critical factor in project delivery. In this session, Migra Teknik used the emazys Z300 PVT to commission a SolarFuture solar park in Denmark, achieving a record throughput of just over 0.5 MW tested per hour across 187 strings and 5,984 modules.
The result demonstrates how the Z300 enables professional commissioning teams to work at the pace that large-scale solar projects demand. With an average test time of 1 minute 37 seconds per string, the instrument fits naturally into a fast-moving commissioning workflow without compromising data quality.
According to Migra Teknik, the collaboration with emazys allows them to test and verify that all components in a solar park are working harmoniously before grid connection, identifying and addressing any issues before the system begins generating power.